Round Concrete Footing Calculator
Calculate concrete volume and bag count for several groups of round footings with different diameters and depths.
How to use this calculator
Use the actual diameter and filled depth of each group of round holes. Add a separate group for a different size. Enter the mixed yield shown on the product bag or datasheet. It is a volume and is different from the dry bag weight.
Formula
One round footing has volume π × (diameter ÷ 2)² × filled depth. Multiply by the count in each group, sum the groups, add the allowance, and divide by the mixed yield per bag. Round up to whole bags.
Reference: QUIKRETE Concrete Mix technical data
Calculator credits
Calculator developmentJulia Edwards
Editorial supervisionSamad Aslam Khan
Expert reviewHammad AhmadFounder ThaykaydarSaab - Online Construction Platform
Published byThe Calculatorz
Last updated
Read how we research, test, review and correct our calculators in our editorial policy.
Frequently asked questions
Can this calculator tell me the correct footing depth?
Use it to estimate concrete from dimensions already specified for your project. Structural design, footing dimensions and local code requirements need separate verification.
What if the post displaces concrete?
This estimate treats each hole as an empty cylinder. A post that extends into the concrete displaces some of the volume. Uneven holes may use more.
How many bags of concrete do I need?
Divide the total volume, including the allowance, by the yield printed on the bag. Bag yields vary by size and product, so always use the manufacturer's stated yield for the exact mix you are buying.
Should I mix concrete by hand or order ready-mix?
Bagged concrete suits small jobs such as a few post footings. For larger volumes, ready-mixed concrete delivered by truck is usually faster and more consistent; many suppliers have a minimum order, so compare the cost of both.
How long does concrete take to cure?
Concrete usually sets enough to walk on within a day, but it gains strength slowly. Most mixes reach about 70% of their design strength in 7 days and full design strength around 28 days, so avoid heavy loads on new footings until the manufacturer's stated time has passed.
What is the difference between concrete and cement?
Cement is the powder that binds concrete together. Concrete is a mix of cement, sand, gravel or crushed stone, and water. Bagged concrete mixes already contain all the dry ingredients, so you only add water.
References & methodology sources
These sources support the calculator’s formula, definitions, thresholds, units or result interpretation.
- QUIKRETE Companies. (2023). Concrete mix 1101: Technical data sheet. View source
- American Concrete Institute. (2022). ACI PRC-211.1-22: Selecting proportions for normal-density and high-density concrete—Guide. View source
- American Concrete Institute. (2019). Building code requirements for structural concrete (ACI 318-19) and commentary. View source
- Peurifoy, R. L., Oberlender, G. D., & Garold, D. (2018). Estimating construction costs (6th ed.). McGraw Hill. View source
- Thompson, A., & Taylor, B. N. (2008). Guide for the use of the International System of Units (SI) (NIST Special Publication 811). National Institute of Standards and Technology. View source